Drax, Brookfield and Radiant plan a 1 GW AI data center in Yorkshire with no tenant yet
By Himanshu Sakre·
Drax announced on November 3, 2026 a partnership with Brookfield and Radiant for a data center of more than 1 gigawatt at its North Yorkshire power station. Total investment could top £20 billion, but planning, grid and a tenant are still missing.
The most ambitious AI data center proposed in Britain so far sits on one of the country's biggest power stations. On November 3, 2026, Drax Group said it had signed an agreement with Brookfield and Radiant, Brookfield's UK neocloud platform, to develop an AI data center of more than 1 gigawatt on the Drax Power Station estate in North Yorkshire. Brookfield estimates total investment could exceed £20 billion ($26.8 billion), including semiconductors.
That is a large number attached to a project at the earliest stage. Here is what is firm, what is conditional and what is missing.
What was announced
CNBC reported the deal on the morning of November 3, 2026. The structure is a phased build.
- Phase 1: up to 100 MW, operational from Q1 2028 on grid power, with an initial £2.5 billion of investment.
- A further 500 MW planned between 2028 and 2031.
- An aim of securing more than 1 GW at the site, with no date given.
Drax's own page on the project describes a "strategic partnership for development of >1GW data centre" and cites two site assets: 4 GW of grid access and 2.6 GW of active dispatchable generation and cooling systems. Drax describes Radiant as Brookfield's UK-headquartered AI infrastructure platform, and the three partners will jointly develop, deliver and operate the site.
What is conditional
Start with the money. The £20 billion is a ceiling, not a budget. CNBC's wording is that total investment "could exceed" that sum, and the only specific commitment is the £2.5 billion for phase 1, which is about one-eighth of the headline. Everything beyond phase 1 is a plan to be decided later, after a tenant is found.
CNBC's reporting is plain on the conditions. Phase 1 depends on planning, regulatory and network approvals, and on securing a tenant. Final investment decisions have not been made. Nothing has been built, and the agreement is to develop.
The tenant point is the one to weigh most. A data center without an anchor customer is a speculative building. Developers of this size usually look for a large customer committed before construction, because the hardware is the biggest line in the bill. The £20 billion figure explicitly includes semiconductors, so most of the headline is hardware that someone else would have to buy and operate.
“This is a unique opportunity for the UK's AI ecosystem to build at scale,”

Why Yorkshire, and why Drax
Power is the whole argument. CNBC notes that the United Kingdom has faced high energy costs and long waits for grid connections. Drax already has a connection, and Drax chief executive Will Gardiner makes the pitch directly on the company's page: "Drax Power Station is one of the few UK sites that can provide large-scale reliable power directly to data centre customers by utilising existing and underutilised generation capacity."
That is a real advantage. A site with an energized 4 GW connection skips years of queueing that sink other projects. Investors noticed: Drax shares rose about 8% in early trading, per CNBC.
The honest caveat is that phase 1 runs on grid power, not on Drax's own generation. Drax's page says the project would use the station's 2.6 GW of dispatchable generation, but the arrangements for that were not detailed in the sources we opened. Until they are, the "power station data center" framing may overstate how much of the plant feeds it.
The context that makes this notable
The announcement lands two weeks after the cautionary example. In October 2026 the Telegraph reported that Microsoft had pulled out of a deal to anchor an Nscale data center near London because of grid delays, as CNBC recounts. Nscale told CNBC it remained "committed" to its UK project and was "exploring alternative power sources for the site." We covered the grid problem at the Loughton site, where the connection date slipped into the 2030s.
Set the two stories side by side and the pattern is clear: money is available, and energized sites are the scarce part. Drax is pitching itself as one of the few that already has one.
How big is 100 megawatts
For comparison, the AI Growth Zone campus at Lanarkshire in Scotland is being built as two 40 MW facilities, DV1 and DV3, leased to CoreWeave for 15 years, per The Register in August 2026. Phase 1 at Drax would be larger than either, and the full 1 GW aim would be many times bigger again. The government's wider push on compute is covered in our report on the UK AI package.
Scale matters here for the sovereign AI argument. A country that wants to train or serve frontier models on its own soil needs sites at this size, with power that is both large and cheap enough to compete with Finland, where Google said in September 2026 it would invest at least €13 billion ($15.1 billion). Our explainer on what sovereign AI means separates funded projects from announced ones. This is announced.
Our take
We would rate this as a serious proposal and a small fact. The site is real, the power connection is real, and the sponsors have the balance sheet. A tenant, a planning decision and a final investment decision are none of those things yet, and each can fail independently.
Watch for three events, in order: a named anchor customer, a planning submission, and a firm date for the grid works behind the Q1 2028 target. If all three arrive, this becomes the most important AI site in the country. If the first one stalls, it joins the long list of data centers that were announced and never energized.
One sourcing note: CNBC's account does not link a Drax or Brookfield press release, and the project figures come from CNBC and Drax's own web page.
Frequently asked questions
What is the Drax Brookfield Radiant data center?
A planned AI data center of more than 1 GW on the Drax Power Station estate in North Yorkshire, announced November 3, 2026. Drax supplies land, power and grid access, Radiant leads AI infrastructure and Brookfield brings capital. It is an agreement to develop, not a built facility.
How much will the Drax AI data center cost?
Brookfield estimates total investment could exceed £20 billion ($26.8 billion), including semiconductors, per CNBC. Phase 1 is an initial £2.5 billion for up to 100 MW. No final investment decision has been made, so the larger figure is potential, not committed spending.
When will the Drax data center open?
Phase 1, up to 100 MW on grid power, is targeted for Q1 2028, per CNBC. A further 500 MW is planned between 2028 and 2031. All of it depends on planning, regulatory and network approvals and on securing a tenant.
Does Drax have a customer for the data center?
Not yet, according to CNBC. Securing a tenant is one of the stated conditions for phase 1. Radiant is seeking customers, and no hyperscaler or AI lab has been named in the reporting we reviewed.
Why are UK AI data centers hard to build?
CNBC points to high energy costs and long waits for grid connections. In October 2026 the Telegraph reported Microsoft pulled out of an Nscale deal near London over grid delays. Drax argues its existing 4 GW grid access avoids that queue.
Sources
What each one is, and whose it is.
- 1
Brookfield targets $27 billion AI data center at power station. Energy firm Drax surges 8%, CNBC (November 3, 2026)
Press reportIndependent of the vendor - 2
Powering AI and Data Centres, Drax Group (November 3, 2026)
OtherThe vendor’s own - 3
Scotland's AI Growth Zone gets a wee £300M power-up, The Register (August 19, 2026)
Press reportIndependent of the vendor