Google's $17 billion Wyoming data center: Crusoe sells the site and the power plan comes into view
By Himanshu Sakre·
Google confirmed a $17 billion data center near Cheyenne on November 5, and Crusoe confirmed the sale of its unfinished site the next day. The price is undisclosed and the carbon capture claim has no number behind it yet.
Google said on November 5, 2026 that it is building its first data center in Wyoming, a $17 billion commitment in Cheyenne and Laramie County. A day later Crusoe, the developer that started the project, confirmed it has sold the site to Google. The sale price was not disclosed by either company, which makes this a story about who now carries the risk, not about a headline number.
The Google data center in Wyoming is worth reading closely because it shows how the frontier compute race is now fought in utility filings and site swaps, not only in chip orders.
What each company actually announced
Google's own post, dated November 5, gives the $17 billion figure and names its partners: Tallgrass Energy, Black Hills Energy, American Electric Power (AEP) and Related Digital. It says the facility will be air-cooled to "minimize strain on local water resources" and that it expects hundreds of millions of dollars in local property taxes for Laramie County and its school district. The post does not give a job count and does not give the campus's planned capacity in megawatts.
Crusoe's update, dated November 6, is shorter. The company says the sale completes its pre-development work on the project: site selection, government approvals and a power strategy. Chase Lochmiller, Crusoe's CEO, said the company has "set up the Wyoming project for construction and eventual operation." Crusoe also says it is developing Google's campus in Armstrong County, Texas, near Amarillo, so the relationship continues.
TechCrunch, reporting the same day, adds the part neither company volunteers. Crusoe first announced the Wyoming project in 2025 with Tallgrass, and it was reportedly meant to scale to 10 gigawatts. Bloomberg reported in June 2026 that Google had raised concerns about cost and construction timeline under Crusoe's management. Google did not say what it paid.
The power plan
The power is where the scale sits. Google says AEP contracted a 702 MW fuel cell development, using natural gas and Bloom Energy fuel cells, with carbon capture and storage. Captured carbon would go to Tallgrass's nearby Eastern Wyoming Sequestration Hub. Google also buys power from gas generators run by Tallgrass and Black Hills, and says it is studying capture for Tallgrass's combined cycle turbines.
Data Center Frontier, reporting on November 4, puts numbers around the AEP piece: roughly $4 billion of AEP capital, a 20-year power purchase agreement with Google, construction expected to start before the end of 2026 and full operation targeted for late 2028. Pricing under the agreement has not been disclosed. The same report says Black Hills agreed in October to serve the campus with up to 590 MW of grid-connected power plus about 2.1 GW of third-party resources managed through a private microgrid, and warns readers not to add the AEP and Black Hills figures together because it is unclear whether they overlap.
“Crusoe is in the business of activating gigawatts for intelligence.”
That caution matters. A reader who sums 702 MW, 2.1 GW and the Tallgrass turbines will get a number nobody has published.

The claim that is not yet a number
Google calls the plant the largest of its kind planned so far. It says carbon capture will remove "a large majority" of the plant's emissions, a phrase TNW notes comes with no figure. Data Center Frontier says the capture rate, the capture equipment supplier and the transport and storage arrangements have not been disclosed. Bloom Energy's fuel cells produce a more concentrated carbon dioxide stream, which could make capture easier, but that is an argument for feasibility, not a result.
So the honest description today is: a very large gas-fired power plan with a capture ambition attached. If the capture works as designed, it is a meaningful template. If it slips, the campus still runs on gas.
Local conditions
TNW notes that Google announced the project two days after voters rejected data centers in 40 of 41 local ballot measures, and that in July Cheyenne halted some data center water discharges after a Meta contractor released a rare bacterium into the city's wastewater reuse system. More than 200 residents attended a community meeting, and Google and its partners are forming a community council. Google's commitment is blunt: "We will pay for 100% of the power we use."
That pledge answers the grid-cost objection that sits behind much of the backlash we track in our data center backlash tracker. It does not answer the water, land or emissions questions on its own.
Where this fits in the capex race
Alphabet's third-quarter results already showed the cost of this build-out: see our look at Alphabet's capex and negative free cash flow. A $17 billion site is a small part of that spend, but it is a site where a partner developer was replaced, which is a data point about how hard these projects are to deliver on schedule.
What we still do not know
Even with two company posts and three outside reports, the basic ledger has blanks. Neither company gave the sale price. Google gave no capacity for the campus and no job count. Nobody has published the capture rate for the fuel cells, or a construction schedule for the data center buildings themselves, as distinct from the AEP plant.
Data Center Frontier fills in some of the physical detail. The campus, which it calls Project Tembo and which was formerly Project Jade, covers about 716 acres in the Switchgrass Industrial Park, with four planned buildings totaling about 3.08 million square feet. It reports that Crusoe withdrew in 2026 and that Google, through Jupiter Star Holdings LLC, is now responsible for the project. Separately, Tallgrass's Cheyenne power hub involves more than $7 billion of investment, and Mitsubishi Power identified two turbines for about 1,150 MW of initial-phase generation in May 2026.
Those are separate pieces of a larger power system, and the reporting is explicit that they should not simply be added up.
Our take
Believe the money and the contracts, because they are in Google and AEP documents. Wait on the climate claim. The thing to watch is not the next announcement but the first filing that states a capture rate, a storage permit and a start date. Until then, Wyoming is a large gas project with a promising add-on, and the sale price hidden from view is the detail most worth chasing.
Frequently asked questions
What is Google building in Wyoming?
Google announced on November 5, 2026 a $17 billion investment in its first Wyoming data center, in Cheyenne and Laramie County. It will be air-cooled, and Google says it will pay for 100% of the power it uses.
Did Crusoe sell its Wyoming data center to Google?
Yes. Crusoe confirmed on November 6, 2026 that it sold its Wyoming site to Google. Neither company disclosed the price. TechCrunch reported that Google had raised cost and timeline concerns, per a June Bloomberg report.
How much power will the Google Wyoming campus use?
Google has not published the campus capacity. It cites a 702 MW AEP fuel cell development, and Data Center Frontier reports separate Black Hills contracts of up to 590 MW grid-connected plus about 2.1 GW of third-party resources, which may overlap.
Will the Wyoming data center be carbon neutral?
Not as announced. Google says carbon capture will remove "a large majority" of the fuel cell plant's emissions but gave no figure. Capture rate, equipment supplier and storage arrangements were not disclosed, per Data Center Frontier.
Who supplies the fuel cells for Google's Wyoming plant?
Bloom Energy supplies the solid oxide fuel cells, and AEP owns about 92% of the project company, with funds advised by Basalt Infrastructure Partners holding the rest, per Data Center Frontier.
When will the Wyoming fuel cell plant be running?
AEP targets full operation in late 2028, with construction expected to start before the end of 2026, according to Data Center Frontier's November 4 report.
Sources
What each one is, and whose it is.
- 1
Google's first Wyoming data center, Google (November 5, 2026)
Vendor announcement - 2
Crusoe Wyoming data center campus update, Crusoe (November 6, 2026)
Vendor announcement - 3
Crusoe sells troubled Wyoming data center project to Google, TechCrunch (November 6, 2026)
Press reportIndependent of the vendor - 4
Google's first Wyoming data centre will run on gas with carbon capture, The Next Web (November 5, 2026)
Press reportIndependent of the vendor - 5
AEP, Google advance $4 billion fuel-cell project to power Cheyenne data centers, Data Center Frontier (November 4, 2026)
Press reportIndependent of the vendor