Nvidia's $105 billion OpenAI guarantee: Kress says it can vanish if the project stalls
By Yash Malviya·
On the November 17, 2026 earnings call, interim CEO Colette Kress said Nvidia's Ohio lease guarantee for OpenAI only starts once financing is secured. Here is what is confirmed and what is not.
Nvidia has guaranteed up to $105 billion of leases for an OpenAI data center campus in Ohio, and its interim chief executive has now said on the record that the guarantee can disappear. On the November 17, 2026 earnings call, Colette Kress explained that the backstop only takes effect once the customer has secured financing and the buildout is real. This is what is known, what is reported, and what is still unclear.
What was guaranteed
TechCrunch reported on November 18, 2026 that the guarantee, announced in August, covers OpenAI's PORTS-Pike data center campus in Ohio, and that OpenAI reportedly agreed the campus would use only Nvidia equipment in exchange. Dataconomy, citing disclosed terms without linking to a filing, says the campus is expected to reach 4.25 gigawatts of initial capacity, that the arrangement runs through SB Energy, and that the $105 billion is most of the $118 billion in data center guarantees Nvidia has disclosed.
Treat the $118 billion total with care. We could not open the underlying disclosure, and Dataconomy itself notes no payments had been made under the Ohio guarantees as of late November 2026. The $105 billion figure is corroborated by TechCrunch.
The structure, as reported, is a residual-value lease guarantee. It applies if OpenAI defaults or becomes insolvent and is meant to cover lease shortfalls. A reimbursement requirement ties to any payment Nvidia makes. Dataconomy says Nvidia's expected exposure begins in fiscal 2029.
What Kress said
Kress described the points on the earnings call and in the CFO commentary as a clarification of existing terms, not a policy change, according to TechCrunch. The guarantee only takes effect once the customer has secured financing to build the facility and install Nvidia products. If the project is delayed or runs into building challenges, she said: "our guarantee doesn't exist anymore." On the financing, she said: "There is the raising of capital that they may need through equity and or debt."
She also said Nvidia will be more selective. Land, power and shell availability will be a top priority, and the company is "taking a very strong look in terms of the types of companies" it would help finance. TechCrunch notes that these terms had never been public before.
“our guarantee doesn't exist anymore”

The context: a company in transition
The same earnings release, dated November 17, 2026 for the quarter ended October 25, shows why Nvidia can offer such guarantees. Nvidia reported revenue of $115.8 billion, up 103% from a year earlier, and data center revenue of $107.6 billion, up 110%. GAAP net income was $65.3 billion. Kress, quoted as interim chief executive and CFO, said "Our momentum is real."
The interim title is itself news. We reported that Jensen Huang resigned as CEO days before the results, and that Nvidia stopped H200 sales to China in the same call. TechCrunch also reported that 197,000 people, including Elon Musk, signed a petition asking Nvidia to reinstate Huang. It reported, citing The Information, that Kress cut the OpenAI guarantee from $250 billion to $105 billion. That reduction is reported, not confirmed by Nvidia in the documents we opened.
Why people call it circular
The worry is simple. Nvidia sells the chips, invests in the buyer and backs the lease on the buyer's building. TechCrunch links to a July 27, 2026 Bloomberg piece on Nvidia's roughly $750 billion of deals and the fear of circular financing. In February 2026, according to Dataconomy, OpenAI closed a $110 billion round at a $730 billion pre-money valuation with $30 billion from Nvidia, and that investment replaced the staged framework announced in September 2025. Nvidia's stake moves with OpenAI's valuation, and the guarantee is a contingent liability on top.
A contingent liability is not a loss. Nothing has been paid, and the revenue Nvidia books from the chips is real cash. The risk is correlation: if OpenAI's finances weaken, Nvidia is hit through its equity, its guarantee and its future orders at once.
What the clarification changes
Read at face value, Kress narrowed the risk. A guarantee that only exists once financing is secured and construction is on track is closer to a completion backstop for lenders than an open-ended promise. It tells banks that Nvidia's name is behind the lease, but only for projects that are real.
It also tells the market something about power. Land, power and shell availability are now the gating inputs for new financing, which fits what we have reported on Ohio voters banning data center projects. A campus the local community rejects is a guarantee that never starts.
What to watch next
Three dates and documents matter. The first is Nvidia's next quarterly CFO commentary, where any payment under a guarantee would have to be disclosed. The second is any filing from OpenAI or SB Energy that describes the lease terms from the other side of the contract, which would let outsiders check Nvidia's description. The third is the power question: whether the Ohio campus actually secures the grid capacity a 4.25 gigawatt site needs, since Kress named power as a top priority for future financing. A guarantee is only as good as the building it backs.
Our take
The disclosure is a step toward transparency, but the picture is still incomplete. We would ask for the guarantee terms in a filing we can read, the exact definition of "secured financing," and a statement of the total exposure across all customers. Until then, treat the $105 billion as a ceiling, the $118 billion as unverified, and the Kress quotes as the strongest evidence on the table. Watch the next quarterly commentary for any payment under a guarantee, which would turn this from a footnote into a story.
Frequently asked questions
What is Nvidia's Ohio guarantee for OpenAI?
TechCrunch reports a $105 billion guarantee for OpenAI's PORTS-Pike data center campus in Ohio, announced in August 2026, with OpenAI reportedly agreeing to use only Nvidia equipment. Dataconomy describes it as a residual-value lease guarantee.
What did Colette Kress say about the guarantee?
She said the guarantee only takes effect once the customer has secured financing and the buildout is real. If the project is delayed or hits building challenges, she said, 'our guarantee doesn't exist anymore,' per TechCrunch.
Has Nvidia paid anything under the guarantee?
Dataconomy reports no payments had been made under guarantees tied to the Ohio campus as of late November 2026, with exposure expected to begin in fiscal 2029. We could not confirm this in a filing.
Why is Nvidia's OpenAI financing called circular?
Nvidia sells chips, invests in OpenAI and backs the lease on its building. TechCrunch links to a July 27, 2026 Bloomberg piece on that concern. Dataconomy says Nvidia put $30 billion into OpenAI's February round.
Is the $118 billion total guarantee figure confirmed?
No. It comes from Dataconomy, which does not link a filing, and we could not open Nvidia's disclosure. The $105 billion Ohio figure is corroborated by TechCrunch.
Sources
What each one is, and whose it is.
- 1
NVIDIA announces financial results for third quarter fiscal 2027, NVIDIA (November 17, 2026)
FilingThe vendor’s own - 2
Nvidia clarifies when it will, and won't, keep financing neoclouds, TechCrunch (November 18, 2026)
Press reportIndependent of the vendor - 3
Nvidia backs OpenAI with $105 billion Ohio data center guarantees, Dataconomy (November 25, 2026)
Press reportIndependent of the vendor